Non-Compliance detail


  
Summary
 
Licence number: 12003
Annual Return Start: 22 Dec 2018
Annual Return End: 21 Dec 2019
Date Received: 12 Feb 2020
 
Licence Condition numberType of non-complianceEPA actionsNo. of times occurred
M2-Requirement to mo Prior to monitoring being undertaken at point 3 (Compressor 3), a mechanical failure was encountered which shut the compressor down. Quarterly monitoring was unable to be undertaken in accordance with the licence due to compressor remaining offline. EPA to monitor future compliance with this condition 1